Non-repayable grant for energy efficiency and energy-saving actions in companies in Castile and León.
The application deadline ends on December 4.
The Regional Ministry of Economy and Finance of Castile and León has opened calls for grants aimed at the IMPROVEMENT OF ENERGY EFFICIENCY IN THE BUSINESS SECTOR, with the purpose of promoting investments in the region in energy saving and energy efficiency within the business sector, seeking the use of the best available technology (BAT), and provided that neither the replaced installation nor the new installation is powered by a renewable energy source.
The main characteristics of this aid programme are set forth below:
BENEFICIARIES
Large companies and SMEs in Castile and León, self-employed professionals, and farmers and livestock breeders. In all cases, the location where the subsidisable action is carried out must be in Castile and León, regardless of the company’s registered office.
The energy extractive industry, oil refining, nuclear fuel processing, and the generation, transmission and distribution of electricity are excluded.
PROJECT TYPES
I. Energy-consuming equipment: replacement of the lighting system, replacement of lifts and escalators, and replacement of energy-consuming equipment with other energy-consuming equipment that delivers energy savings or improves energy efficiency.
II. Replacement and/or installation of energy variable control systems.
III. Installation of thermal effluent recovery units.
IV. Implementation of energy management systems, based on the UNE EN-ISO 50001 standard.
PROJECT REQUIREMENTS
- Incentive effect.
- The deadline to carry out the actions is 2019-10-02.
- Installations whose fuel after replacement is solid fossil fuel (coal) are not eligible for funding.
ELIGIBLE COSTS
- Cost of equipment, materials and installations.
- Cost of transport and assembly and the cost of commissioning.
- Costs of civil works and building permits and associated engineering projects and preliminary studies.
- In the case of buildings, an energy efficiency certificate prior to the action and its update.
- Cost of implementing energy management systems and control systems.
- Cost of energy studies or audits and cost allocators.
TYPE AND INTENSITY OF AID
Non-repayable grant (subject to the de minimis regime).
For actions I, II and III indicated in the ‘Types of projects’ section, the grant amount will not exceed 40% of the eligible expenditure, nor will it be less than 15% of that cost, and the maximum amount of the grant will not exceed €200,000. The aid percentage is calculated based on the energy savings.
For action IV, the grant amount will not exceed 75% of the eligible expenditure. The maximum grant amount will not exceed €10,000.
SUBMISSION DEADLINE
Currently open, until 2018-12-04. Budget allocation: €1,856,950.